- Capacity: 300 ton per day
- Warranty period: 1 year
- Work pressure: see drawings
- Max. work temperature: see drawings
- Operating ambient temperature: see drawings
- Installation type: site assembly
- Main process theory: esterification, ester-exchange, ester distillation, methanol recovery, glycerin recovery, and so on.
- Design working life: 20 years
Delivery List
- Boiler
- Reactor
- Towers/columns
- Heat exchange units
- Medium tanks
- Vacuum unit
- Tail gas buffer tank
- Tail gas recovery and burning unit
- Smoke de-sulfur tower
- Pipelines and pipe fittings in the battery limit
- Instrument and meters
- Valves
- Safety valves
- Sight glass
- gaskets, bolts and nuts
- Fans and pumps
- Electric control cabinet
- electric cables in the battery limit